| SUBMITTAL CHECKLIST
DEMOLITION OF A STRUCTURE |
OPB Operations
250 Frank H. Ogawa Plaza 2nd Floor Oakland, CA 94612 |
|
|
||
| This checklist provides a general guideline of documents which are normally required to apply for permits related to the demolition of a structure. Check at the Permit Counter to verify the submittal documents which may be specific to your individual project. | ||
| # Copies | Document | DESCRIPTION OF DOCUMENTS | |
| 1 | Proof of Property Ownership | Grant Deed or current property not receipt (if applicant is owner) | |
| 1 | Utility terminations | Evidence that all utilities have been capped (including sewer connections) or that you have applied for all applicable permits | |
| 1 | Driveway removal | Evidence that the curb, parking strip and sidewalk have been restored or that you have applied for all applicable permits | |
| 1 | Demolition security | Demolition security equal to $2,000 (if you do not have a valid demolition license) | |
| 1 | BAAQMD form | Signed "Acknowledgement of Bay Area Air Quality Management District Notification" form. | |
| 1 | Contractor's license | Current contractor's license (if a contractor) | |
| 1 | Business license | Current City of Oakland Business License (if a contractor) | |
| 1 | Permit application worksheet | Completed permit application worksheet for applicable permit(s) | |
| other |
| Other submitted checklists available: | Minor Repairs and Minor Alterations
Repairs, Alterations and Minor Additions Major Repairs, Alterations and Additions Planning and Building Review (Track Group 1)* |
Engineering permits (track Group 3)*
New Construction (Track Group 7)* Major Building Development (Track Group 8)* Land Subdivisions (Track Group 9)* |
| *available at Permit Counter |